BUILDING: Green Point Stadium Progress

 



Recent Western Cape Business News

The slow and complex procedure of raising the inner ring of the Green Point stadium roof has been completed. This marks another milestone on the route to the 2010 World Cup which starts in June next year.

The process of tightening the “spokes” and raising the inner ring of the roof structure from ground level to a height of 34,5 metres began on Monday 9 February and was successfully completed on Wednesday 18 February.

Mike Marsden, Executive Director responsible for 2010 with the City of Cape Town, said that the inner Tension Ring had been successfully installed by using hydraulic jacks that progressively tightened the 72 cables connecting the inner and outer rings of the roof. A total of 7,4 km of cabling weighing 370 tons was raised.

The operation was closely monitored by the City's structural engineers who expressed their satisfaction. The next phase is the positioning of steel trusses, the installation of the 9000 pieces that make up the glass roof surface, and the attachment of a fabric membrane below the roof. The 4500-ton roof is scheduled for completion in September 2009.

Attached to the inner tension ring of the roof will be a "ring of fire" which includes the stadium floodlights and an extension that will light the stands. The pitch itself will not be covered.

Rainfall run-off from the roof will be collected in ponds and used for the irrigation of the golf course on the surrounding Green Point Common.

Marsden said the roof had been designed to comply with stringent environmental requirements relating to acoustic dampening, aesthetics and the floodlighting. The roof also complied with FIFA's technical requirements in terms of spectator coverage. “A major advantage of the design is that there are no cables or structural elements that could cast a shadow on the pitch during matches,” he said.

The next major stadium projects, says Marsden, are the construction of the outer façade, the seating, furniture and fittings and finally the laying of the grass pitch which is being carefully cultivated in Stellenbosch in compliance with Fifa requirements.

Marsden said the stadium was on track for completion on 14 December 2009.


 
 
 
freight-and-shipping-services-western-capenorths-garden-furnitureBusiness Profilesdecor-and-furniture-cape-townBubble-Chairs
 
   
 
 
 
  Accomodation
Accommodation


Online Foreign Exchange
Foreign Exchange


Directory
Directory


Fax
Fax 2 Email


Finance
Finance


Furniture
Furniture


Casino
Online Casino


Restaurant
Restaurant


Auctions
Shop Online


Study IT
Study IT Online


Web design
Web Design


Weddings
Weddings


Work
Work from Home
 
 
 
 
 
Company News
 
 

 

© 2017 www.wcbn.co.za. All rights reserved.

Daily Newsletter Subscription

 

Subscribe to the Western Cape Business News Daily News and information email (it's free).

Thank You
Your email address has been added.

Name:
Email Address: