SHIPPING: CT Terminals Beaver Ahead

 



Recent Western Cape Business News

THE R5.4 billion, five-year expansion programme at the Cape Town container terminal continues to transform the facility with the aim to be capable of handling nearly double its existing cargo capacity by 2012.

Major dredging, deepening and refurbishment work on the second of four berths is well underway and will be completed by May next year. The first 100m of Berth 602 has been handed over recently to terminal operations. Coupled with the already refurbished Berth 601, this affords the terminal 420m of berth space to accommodate one large 305m vessel along its long quay.

Says Transnet Port Terminal’s (TPT) Western Province terminal executive, Velile Dube, “There have been some challenges. Most significant of these is the complexity of maintaining uninterrupted operations at the container terminal while it is effectively a construction site.

However we are well on our way towards transforming the container terminal into a modern four berth facility that will assist in meeting the demands of the rapid growth in the container sector.”

The upgrades to all four berths and the Ben Schoeman Basin will enable larger new generation vessels to enter and ‘park’ safely at the container facility.

Inside the terminal, the fleet of harbour cranes has been beefed up to improve the efficiency of container handling. In August, the fifth and sixth Liebherr ship-to-shore cranes were commissioned. With a total of six new Liebherr cranes in place, Berth 601 offers high productivity container handling that is faster and more efficient.

The fleet of straddle carriers in Cape Town is also being phased out in favour of massive rubber-tyred gantry (RTG) cranes, which make better use of limited space by stacking six rows wide, five containers high and 30 deep. To date 20 RTG cranes have been commissioned and handed over to the terminal, with the remaining eight scheduled for handoverby the end of this month.

Refrigerated containers, or reefers, will benefit from the handing over in August of 864 reefer plug points in reefer block 1. The overall expansion programme will result in three reefer stacks with a total of 2 712 reefer points served by gantry cranes.

Human capital development has also been a major aspect of the expansion programme. The terminal’s new cranes necessitated an aggressive training programme for operators of lifting equipment (OLEs), with 33 OLEs joining operations in August and bringing the total number of newly trained OLEs to 120. Additional training in operation of ship-to-shore cranes will take place from January next year.

Dube says the five year expansion project is one of several Transnet projects taking place within South Africa’s container sector, with the aim of creating additional capacity ahead of demand. By 2012, the capacity of the terminal will be 1.4 million TEUs, nearly double its existing 740 000 TEU capability.


 
 
 
engineering-cape-townBusiness Profilesfreight-and-shipping-services-western-capereal-steelnorths-garden-furniture
 
   
 
 
 
  Accomodation
Accommodation


Online Foreign Exchange
Foreign Exchange


Directory
Directory


Fax
Fax 2 Email


Finance
Finance


Furniture
Furniture


Casino
Online Casino


Restaurant
Restaurant


Auctions
Shop Online


Study IT
Study IT Online


Web design
Web Design


Weddings
Weddings


Work
Work from Home
 
 
 
 
 
Company News
 
 

 

© 2019 www.wcbn.co.za. All rights reserved.

Daily Newsletter Subscription

 

Subscribe to the Western Cape Business News Daily News and information email (it's free).

Thank You
Your email address has been added.

Name:
Email Address: